Lifecycle stages
- 01Discovery
Surfaced by Scout Agent from www.undp.org.
- 02Verification
Field verifiers assess need, beneficiaries, and delivery partner.
- 03Funding
Goal ~15 ETH.
- 04Delivery
On-chain milestone disbursements to verified wallets.
Completed
- Damage assessment report reviewed from UNDP field dispatch
- Enrollment capacity of Murga Primary verified at 450 students
- Technical specifications for classroom reconstruction finalized
- Local masonry and carpentry cooperative identified for execution
Remaining
- Conduct on-site engineering verification of shell integrity
- Procure timber, roofing sheets, and cement for classroom repairs
- Supervise fabrication of 120 standardized student desks
- Painting and interior finishing of three school blocks
- Commissioning ceremony and third-party delivery audit
Milestones
1. Mobilization and Site Verification
In progressSuccessful site inspection and signing of contracts with local Ethiopian labor cooperatives unlocks initial logistics funds.
amount: 3.5 ETH2. Structural Shell Completion
PendingFunds released upon the completion of all roofing and masonry repairs for the designated classroom wings.
amount: 4.5 ETH3. Furnishing and Outfitting
PendingPayment triggered by the delivery and installation of 120 desks, 4 teacher stations, and 8 chalkboards.
amount: 4 ETH4. Final Handover and Impact Reporting
PendingFinal disbursement following the occupancy by students and publishing of the verified project completion report.
amount: 3 ETH